Question 1:

P and Q can complete a work in 9 and 12 days respectively. Working alternatively, in how many days the same work will be completed if Q starts the work.

Question 2:

20 women can do a piece of work in 15 days while 16 men can do the same work in 15 days then find the ratio of efficiency of men to women.

Question 3:

A can complete a work 2 days earlier than B. Together they will complete the work in $4\frac{4}{9}$ days. Find the number of days taken by B to complete the same work.

Question 4:

A takes 10 days more than B to finish a task. They both do the work together for 5 days and finish $\frac{8}{15}$ part of the work. How long will B alone take to complete the whole work?

Question 5:

A and $B$ can do a piece of work in 36 days. $B$ and $C$ can do the same work in 60 days. $A$ and $C$ can do the same work in 45 days. In how many days, can A alone complete the same work?

Question 6:

A, B and C can do a piece of work in 10,12 and 15 days, respectively. In how many days can B do the work, if he is assisted by $A$ and $C$ together on alternate days?

Question 7:

If 25 men can complete a work in 36 hours, then in how many hours will 12 men complete the same work?

Question 8:

18 persons can complete a work in 15 days when they work 6 hours a day. The time (in days) taken by 12 persons working 10 hours a day to complete the same work, is:

Question 9:

Radha who is half as efficient as Kirti, will take 30 days to complete a task if she works alone. If Radha and Kirti work together, how long will they take to complete the task?

Question 10:

$\mathrm{A}$ and $\mathrm{B}$ can do a piece of work in 12 days and 20 days respectively. They both work together for 6 days. The remaining work is completed by $C$ alone in 12 days. In how many days will $A$ and $C$ together complete the $\frac{2}{3}$ part of the work?