Question 1:

Mr. Rajesh is twice as good a worker as Mr. Vishal and together they finish a piece of work in 28 days. In how many days will Vishal alone finish the work?

Question 2:

P is 4 times faster than Q in doing a job. Q takes 27 more days than P to finish the job. If they work together, in how many days will the work be finished?

Question 3:

A and B working together can do 55% of the work in 11 days. A alone can do the work in 25 days. How many days will B alone take to do the same work?

Question 4:

20 persons were engaged to complete a work in 8 days. Due to COVID 19 infection, 4 persons left the job after 4 days. The total number of days required to complete the work is:

Question 5:

A can complete 60% of a work in 6 days and B can complete the same work in 15 days. They work together for 3 days. The remaining work is completed by C alone in 12 days. In how many days will C alone complete $\frac{1}{8}$ part of the same work?

Question 6:

A, B and $\mathrm{C}$ can do a work in 8,10 and 12 days, respectively. After completing the work together, they received ₹ 5,550. What is the share of B (in ₹) in the amount received?

Question 7:

A can complete a project in 10 days and B can complete the same project in 15 days. If A and B start working on the project together and B quits 5 days before the project is completed, in how many days will the project be completed?

Question 8:

$\mathrm{A}$ and $\mathrm{B}$ can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete $\frac{4}{9}$ part of the original work in:

Question 9:

10 women can complete a work in 15 days. The same work can be completed in 5 days by 15 men. 10 women started the work and after 3 days, 5 men replaced 5 women. In how many days will the work be completed?

Question 10:

Person A takes 28 hours to complete a work. Person B completes the same work in one-fourth of the time taken by A. If the two persons work together; in how much time will the work be completed?