Practice questions here, for every subject and every exam. Unlimited questions for unlimited attempts, given with answers and explanations.
$\mathrm{P}, \mathrm{Q}$ and $\mathrm{R}$ can do a piece of work in 30 days 45 days and 10 days respectively. But they decided to work one at a time each day starting with $\mathrm{P}$ and receive Rs.5400 towards their remuneration. Find the amount received by R.
They work alternatively
The wage will be distributed on the basis of part of work done by them.
P will work for 7 days
Work done by $\mathrm{P}=3 \times 7=21$
$Q$ will work for 7 days
work done by $Q=2 \times 7=14$
$\mathrm{R}$ will work for $6 \frac{1}{9}$ days
Work done by $R=9 \times \frac{55}{9}=55$
Ratio of work done
$\mathrm{P} \quad \mathrm{Q} \quad \mathrm{R}$
$21: 14: 55$
90 unit $= Rs 5400$
$\mathrm{R}=55\times60$ unit $=$ Rs $.3300$
If A works alone, he would take 8 days more to complete the job than of both $A$ and $B$ worked together. If B worked alone, he would take 18 days more to complete the job than if A and B work together. How many days would they take to complete the work if both of them worked together?
Let the time taken by $A$ and $B$ to finish the work when working together be ' $x$ ' days
According to the question,
$ \frac{1}{x+8}+\frac{1}{x+18}=\frac{1}{x} $
$\Rightarrow 2 \mathrm{x}^2+26 \mathrm{x}=\mathrm{x}^2+26 \mathrm{x}+144 $
$ \Rightarrow \mathrm{x}^2=144$
$\Rightarrow \mathrm{x}=12$ days
time is taken for both to work together
=12 days
A' alone completes $\frac{4}{5}^{t h}$ part of a work in 20 days. The remaining work then completed by ' $A$ ' and ' $B$ ' working together in 3 days. How long would 'B' alone take to do two times the original work?
Let, total work = 50 unit
A do $4 / 5$ th work $=4 / 5 \times 50=40$ unit
Efficiency of $A=\frac{40}{20}=2$
So,
Work left $=50-40=10$ unit
A's 3 days work $=3 \times 2=6$ unit
Left work $=10-6=4$ unit
Efficiency of $B=\frac{4}{3}$
' $\mathrm{B}$ ' alone take to do two times the original work =
$
\frac{100}{\frac{4}{3}}=\frac{300}{4}=75 \text { days }
$
A and B together can complete a piece of work in 16 days. They worked together for 7 days and then A alone finished the remaining work in 21 days. B alone can complete the work in ___ days.
Clearly, in 7 days working together A$\&$B will do $\frac{7}{16}$ part of the work
$ \frac{9}{16}$ work is done by A alone in 21 days
Total work is done by A alone in $21 \times \frac{16}{9}$ $=\frac{112}{3}$ days
Now,
B's 1 day work $=7-3=4$ unit
Required time $=\frac{112}{4}=28$ days
A factory requires 42 machines to produce a certain number of articles in 63 days. It is proposed to produce the same number of articles in 54 days, using ${x}$ machines. The value of $4 x$ is:
According to question
$42 \times 63=x \times 54$
$x=\frac{42 \times 63}{54}=49$
Hence, $4 x=4 \times 49=196$
A and B can do a piece of work in 45 and 40 days respectively. They began the work together but A left after some days and $B$ finished the remaining work in 23 days. What is the number of days after which A left the work? ?
A's 1 days' work $=\frac{1}{45}$, B's 1 days' work $=\frac{1}{40}$
A left the work after $x$ days of the start of the work.
Then, Work done by A in $\mathrm{x}$ days $=\frac{\mathrm{x}}{45}$
Work done by B in $(x+23)$ days $=\frac{(x+23)}{40}$
Given,
$\frac{\mathrm{x}}{45}+\frac{(\mathrm{x}+23)}{40}=1$
$\Rightarrow \frac{(8 \mathrm{x}+9 \mathrm{x}+207)}{360}=1$
$\Rightarrow 17 \mathrm{x}=360-207=153 $
$\Rightarrow \mathrm{x}=\frac{153}{17}=9$ days
$\therefore$ A left the work after 9 days.
Amlesh can complete 25% of a work in 15 days. He works for 15 days and then Bablu alone finishes the remaining work in 30 days. In how many days will Amlesh and Bablu working together finish 30% of the same work?
$Amlesh$ completes $25 \%$ of the total work in 15 days, so
Time taken to complete whole work $=\frac{15}{25} \times 100=60$ days
$\mathrm{Bablu}$ completes $75 \%$ of the total work in 30 days, So
Time taken to complete whole work $=\frac{30}{75} \times 100=40$ days
Let the total work be $120,(\mathrm{LCM}$ of 60 and 40$)$
Efficiency of $\mathrm{Amlesh}=\frac{120}{60}=2$
Efficiency of $\mathrm{Bablu}=\frac{120}{40}=3$
So, time taken to complete $30 \%$ of total work $=\frac{30}{100} \times \frac{120}{(2+3)}=\frac{36}{5}=7\frac{1}{5}$ days
A, B and $\mathrm{C}$ can do a work in 12,15 and 18 days, respectively. After completing the work together, they received ₹ 6,660. What is the share of C (in ₹) in the amount received?
Let the total work be 180 . (LCM of 12,15 and 18 )
Efficiency of $\mathrm{A}=\frac{180}{12}=15$
Efficiency of $\mathrm{B}=\frac{180}{15}=12$
Efficiency of $\mathrm{C}=\frac{180}{18}=10$
They worked together, So
Ratio of efficiencies $=$ Ratio of wages
Total wages $=15+12+10=37$ unit
Given that
$37 \rightarrow $₹ 6660
$1 \rightarrow $₹ 180
So, Share ofC
$10 \rightarrow $₹ 1800
A can finish a piece of work in 48 days and B can finish it in 72 days. They work together for 12 days and then A goes away. In how much time (in days and hours) will B finish 25% of the remaining work?
Let the total work be 144 , (LCM of 48 and 72), So
Efficiency of $\mathrm{A}=\frac{144}{48}=3$
Efficiency of $\mathrm{B}=\frac{144}{72}=2$
They worked for 12 days
So, Work completed in 12 days $=12 \times(3+2)=60$
Remaining work $=144-60=84$
So, $25 \%$ of 84 work is to be completed by B
Time $=\frac{25}{100} \times \frac{84}{2}=\frac{21}{2}=10 \frac{1}{2}$ days
Or 10 days $\frac{1}{2} \times 24 h r=10$ days 12hours
X, Y and Z can do a piece of work in 38 days, 76 days and 19 days, respectively. X started the work. Y joined him after 2 days. If Z joined them after 8 days from the beginning, then for how many days did X work?
Let the total work be $76,(\mathrm{LCM}$ of 38,76 and 19 )
So, Efficiency of $\mathrm{X}=\frac{76}{38}=2$
Efficiency of $\mathrm{Y}=\frac{76}{76}=1$
And Efficiency of $\mathrm{Z}=\frac{76}{19}=4$
Let the total time taken by $\mathrm{X}$ to complete the whole work be t, then
$2 \times t+1 \times(t-2)+4 \times(t-8)=76$
$2 t+t-2+4 t-32=76$
$7 t=110$
$t=\frac{110}{7} \mathrm{hr}$
Ratio of efficiency of $\mathrm{A}$ and $\mathrm{B}=50 \%: 100 \%=1: 2$
Total work $=16 \times(1+2)=16 \times 3=48$
So, Time taken by A to complete total work $=\frac{48}{1}=48$ days
According to question
Given, $6 \mathrm{~A}=8 \mathrm{C}$
$
\frac{A}{C}=\frac{4}{3}
$
given, $6 \mathrm{~B}=4 \mathrm{C}$
$
\frac{B}{C}=\frac{2}{3}
$
We get, $\mathrm{A}: \mathrm{B}: \mathrm{C}=4: 2: 3$
Let total work $=54 \times 4=216$ unit
B require time to finish work $=\frac{216}{2}=108$ days
Lcm of 10 and 15 be the total work.
Total efficiency of 1 st and 2 nd $\mathrm{AC}=3+2=5$ unit
Required time to cool the hall together $=\frac{30}{5}=6 \mathrm{~min}$
One day work for $\mathrm{A}$ and $\mathrm{B}=3+2$
$=5$
A and work for 4 days $=5 \times 4$
$=20$
$\begin{aligned} \text { Remainng work } &=36-20 \\ &=16 \end{aligned}$
$A$ and $C$ completed remaining work in 4 days
One day work for $A$ and $C=\frac{16}{4}$
$=4$
Then efficiency of $\mathrm{C}=4$ - efficiency of $\mathrm{A}$
$=4-3$
$=1$
one-third of the work $\begin{aligned} &=\frac{1}{3} \times 36 \\ &=12 \end{aligned}$
$\begin{aligned} \text { C can complete one-third of the same work } &=\frac{12}{1} \text { days } \\ &=12 \text { days } \end{aligned}$
A and B working together can complete a work in 30 days. A alone can complete the same work in 50 days. In how many days can B alone do the same work?
$A+B=30$ days
$A=50$ days
$L C M$ of 50 and 30 will be 150
Then efficiency of $A+B=5$ unit/days
Efficiency of $A=3$ unit/days
Efficiency of $B= 5-3 = 2$ unit/days
B can do alone complete the work $=\frac{\text { total work }}{\text { efficiency of B }}$
$=\frac{150}{2}$
$=75$ days
Let $x$ be the required machine.
According to question
56 Machine $\times 144$ Days $=x \times 96$ Days
$
\begin{aligned}
&\mathrm{x}=\frac{96 \text { Days }}{56 \text { Machine } \times 144 \text { Days }} \\
&\mathrm{x}=84 \text { Machine }
\end{aligned}
$
Let efficiency of $A=10$ unit/day
So, efficiency of B $=9$ unit/day
efficiency of $\mathrm{C}=12 \mathrm{unit} /$ day
Total efficiency of $\mathrm{A}+\mathrm{B}+\mathrm{C}=10+9+12=31$ unit
Total work $=10 \times 15=150$ unit
Work done by $\mathrm{A}+\mathrm{B}+\mathrm{C}$ in 3 days $=31 \times 3=93$ unit
Remaining work 150-93= 57 unit
Work done by D in days $=150 \times \frac{19}{2} \times \frac{1}{57}=25$ days
A factory requires 42 machines to produce a certain number of articles in 63 days. It is proposed to produce the same number of articles in 54 days, using x machines. The value of 3x is:
According to question
$
\begin{aligned}
&42 \times 63=x \times 54 \\
&x=\frac{42 \times 63}{54}=49
\end{aligned}
$
Hence, $3 x=3 \times 49=147$
B is $25 \%$ more efficient than A
So, $\frac{A}{B}=\frac{4}{5}$
$\mathrm{C}$ is $20 \%$ more efficient than $\mathrm{B}$
So, $\frac{B}{C}=\frac{5}{6}$
Comparing $\mathrm{A}, \mathrm{B}$ and $\mathrm{C}$ we get
$\mathrm{A}: \mathrm{B}: \mathrm{C}=4: 5: 6$
Total work $=20 \times 4=80$ unit
$\mathrm{A}$ and $\mathrm{C}$ work together done the work $=(4+6) \times 5=50$
Remaining work $=80-50=30$ unit
B alone will complete the remaining work in days $=\frac{30}{5}=6$ days
Soni and Gita together can complete work in 8 h and Soni alone can complete the work in 12 h. In how many hours can Gita alone complete the work?
Let the Lcm of 8 and 12 be the total work $=24$ unit
Efficiency of Geeta $=3-2=1$
Gita alone will complete the job $=\frac{24}{1} = 24$ hours