Practice questions here, for every subject and every exam. Unlimited questions for unlimited attempts, given with answers and explanations.
A and B can do a work in 30 and 40 days respectively. They began the work together. A left the work after some days and B finished the remaining work in 5 days. After how many days did A leave?
ATQ,
B worked for last 5 days, so work done by $B=15$
Remaining work $=120-15=105$
Work done by both $\mathrm{A}$ and $\mathrm{B}=\frac{105}{7} =15$ days
So $\mathrm{A}$ work for 15 days.
Arti and Rita can do a job in 8 hours (working together at their respective constant rates) and Arti can do the job alone in 10 hours. In how many hours can Rita do the job alone?
Efficiency of Arti and Rita $=5$ units $/ \mathrm{h}$
If Efficiency of Arti = 4 units/h
then Efficiency of Rita $=1$ unit $/ \mathrm{h}$
Total Work $=40$ units
So, time taken by Rita to do the job $=\frac{40}{1}$ h $=40$ h
A can do a piece of work in 40 days. He works at it for 10 days, and then B alone finishes the remaining work in 45 days. In how many days will A and B working together finish 75% of the same work?
According to question
$A \times 40 = A \times 10 + B \times 45$
$A \times 30=B \times 45$
$\frac{A}{B}=\frac{3}{2}$
Total work $=A \times 40=3 \times 40=120$
$75 \%$ of $120=\frac{3}{4} \times 120=90$
Time $=\frac{90}{(3+2)}=\frac{90}{5}=18$ days
John can complete a piece of work in 6 days working 8 hours each day and Manu can complete it in 3 days working 4 hours each day. How long will they take to complete it, working together $9 \frac{3}{5}$ hours a day?
Let the efficiency of John be J and that of Manu be M.
Work done by John = Work done by Manu, So
$J \times 8 \times 6=M \times 3 \times 4$
$\frac{J}{M}=\frac{12}{48}=\frac{1}{4}$, per hour
Total work = $1\times 8 \times 6$ =48 unit
John and Manu complete (1+4)=5 unit in an hour
So, John and Manu's one day's work $=5 \times \frac{48}{5}=48$ unit
Time taken by both to complete the whole work working $9 \frac{3}{5}$ hours daily $=\frac{48}{48}=1$ day
Let the total work be 30, (LCM of 10 & 15), So
Efficiency of $\mathrm{A}=\frac{30}{10}=3$
Efficiency of $\mathrm{B}=\frac{30}{15}=2$
Let the project completed in t days, then
3t+2(t-5)=30
3t+2t-10=30
5t=40
t=8 days
A can do a work in 40 days and B can do the same work in 50 days. They worked together for 5 days and then B left the work. In how many days will A finish of remaining work?
Let A complete the remaining work in x days.
The efficiency of A is 1/40
And the efficiency of B is 1/50
So, the efficiency of A and B together is
⇒ (1/40) + (1/50)
⇒ (5 + 4)/200 = 9/200
A and B worked for 5 days, rest completed by A
⇒ (9/200) × 5 + (1/40) × x = 1
⇒ 9/40 + x/40 = 1
⇒ 9 + x = 40
⇒ x = 31 days
∴ A will complete the rest of the work in 31 days.
Alternate Method
| Time | Total work (LCM of Time) | Efficiency |
A | 40 |
| 5 |
|
| 200 |
|
B | 50 |
| 4 |
The total efficiency of A and B is
⇒ 5 + 4 = 9
They worked for 5 days
⇒ 9 × 5 = 45
Rest of the work completed by A
⇒ (200 - 45)/5 = 31 days.
∴ A will complete the rest of the work in 31 days.
A is 5 times as good a workman as B and is therefore able to complete a job in 52 days less than B. In how many days will they complete it working together?
Let efficiency of A's and B is 5x and x
According to the question,
B-A=52 days
5x-1x=52 days
4x =52 days
x=13 days
So, Total work =13×5=65
A and B complete the work together in $= \frac{65}{6} = 10 \frac{5}{6}$
A can do a piece of work in 45 days. He works for 30 days and leaves. If B completes the remaining work in 5 days, then in how many days can B alone complete the entire work?
A can do a piece of work in 45 days.
A's 1 days work =1/45
A's 30 days work =1/45×30=2/3
The remaining work =1-2/3=1/3
B's complete 1/3 th of work in 5 days
Then, B's 1 day work =1/(3×5)=1/15
B can complete the whole work =15 days
A, B and C can do a piece of work in 10,12 and 15 days, respectively. In how many days can B do the work, if he is assisted by $A$ and $C$ together on alternate days?
Let total work $= 60$ unit
Efficiency of A $= \frac{60}{10}=6$
Efficiency of B $= \frac{60}{12}=5$
Efficiency of C $= \frac{60}{15}=4$
On the first day, B is assisted by A and on the Second day, B is assisted by C and this continues
So in two days $(6+5) + (5+4) = 20$ units of work get completed.
To complete 60 units of work, It will take $2\times3 = 6$ days
5 men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
Let the efficiency of men is $M$ and that of boys is $B$, then
$
(5 M+2 B) \times 30=(7 M+10 B) \times 15
$
$150 M+60 B=105 M+150 B$
$45 M=90 B$
$\frac{M}{B}=\frac{2}{1}$
Total work $=30 \times(5 \times 2+2 \times 1)=30 \times 12=360$
Let the work is now completed by $x$ boys and 40 men in 4 days
So, $\frac{360}{40 \times 2+x}=4$
$
\begin{aligned}
&80+x=90 \\
&x=10
\end{aligned}
$
A can complete 25% of a work in 15 days. He works for 15 days and then B alone finishes the remaining work in 30 days. In how many days will A and B working together finish 50% of the same work?
$A$ completes $25 \%$ of the total work in 15 days, so
Time taken to complete whole work $=\frac{15}{25} \times 100=60$ days
$\mathrm{B}$ completes $75 \%$ of the total work in 30 days, So
Time taken to complete whole work $=\frac{30}{75} \times 100=40$ days
Let the total work be $120,(\mathrm{LCM}$ of 60 and 40$)$
Efficiency of $\mathrm{A}=\frac{120}{60}=2$
Efficiency of $\mathrm{B}=\frac{120}{40}=3$
So, time taken to complete $50 \%$ of total work $=\frac{50}{100} \times \frac{120}{(2+3)}=\frac{1}{2} \times \frac{120}{5}=12$ days
A, B and $\mathrm{C}$ can do a work in 8,10 and 12 days, respectively. After completing the work together, they received ₹ 5,550. What is the share of B (in ₹) in the amount received?
Let the total work be 120 . (LCM of 8,10 and 12 )
Efficiency of $\mathrm{A}=\frac{120}{8}=15$
Efficiency of $\mathrm{B}=\frac{120}{10}=12$
Efficiency of $\mathrm{C}=\frac{120}{12}=10$
They worked together, So
Ratio of efficiencies $=$ Ratio of wages
Total wages $=15+12+10=37$ unit
Given that
$37 \rightarrow $₹ 5550
$1 \rightarrow $₹ 150
So, Share of B
$12 \rightarrow $₹ 1800
Let the total work be 240 , (LCM of 48 and 60), So
Efficiency of $\mathrm{A}=\frac{240}{48}=5$
Efficiency of $\mathrm{B}=\frac{240}{60}=4$
They worked for 12 days
So, Work completed in 12 days $=12 \times(5+4)=108$
Remaining work $=240-108=132$
So, $25 \%$ of 132 work is to be completed by B
Time $=\frac{25}{100} \times \frac{132}{4}=\frac{33}{4}=8 \frac{1}{4}$ days
Or 8 days $\frac{1}{4} \times 24 h r=8$ days 6 hours
A and B can do a piece of work in 25 days. B alone can do $66\frac{ 2}{3}$% of the same work in 30 days. In how many days can A alone do 4/15 part of the same work?
$66 \frac{2}{3} \%$ of work is done by $B$ in 30 days.
$\Rightarrow$ Complete work will be done by $B$ in $\frac{30 \times 3}{2}=45$ days ( as 66 $\frac{2}{3} \%=\frac{2}{3}$ )
Now, Let the total work be $\operatorname{LCM}(25,45)=225$ units
According to question,
Efficiency of $(A+B)=\frac{225}{25}=9$
And, efficiency of $B=\frac{225}{45}=5$
So, efficiency of $A=9-5=4$
$\Rightarrow A$ will do $\frac{4}{15}$ part of the work in $=\frac{\frac{4}{15} \times 225}{4}=15$ days
A and B can do a piece of work in 36 days. B and C can also do the work in 60 days. A and C can do the same work in 45 days. In how many days can B alone complete the same task?
A Let total work be $\operatorname{LCM}(36,60,45)=180$
So, combined efficiency of $A$ and $B=\frac{360}{36}=10$
Also, combined efficiency of $B$ and $C=\frac{360}{60}=6$
And, combined efficiency of $A$ and $C=\frac{360}{45}=8$
$\Rightarrow$ Combined efficiency of $A, B$ and $C=\frac{10+6+8}{2}=12$
$\Rightarrow$ Efficiency of $B=12-8=4$
So, required time $=\frac{360}{4}=90$ days
Let total work be LCM10,5 $=10$
$\Rightarrow$ Efficiency of $A=1010=1$
$\Rightarrow$ Efficiency of $B=105=2$
Now, work done by A and B together in 2 days $=2 \times 1+2=6$
$\Rightarrow$ Work done by A and $\mathrm{C}$ in 3 days $=10-6=4$
$\Rightarrow$ Efficiency of $\mathrm{C}=4-1 \times 33=13$
So, time taken by $\mathrm{C}$ alone to complete $60 \%$ of the work $=0.6 \times 1013=18$ days
Let the efficiency of $A$ be 2 , then efficiency of $B=1$
Now, total work
So, time taken by B alone to complete the workdays
Let the total work be $92,(\mathrm{LCM}$ of 46,92 and 23 )
So, Efficiency of $\mathrm{X}=\frac{92}{46}=2$
Efficiency of $\mathrm{Y}=\frac{92}{92}=1$
And Efficiency of $\mathrm{Z}=\frac{92}{23}=4$
Let the total time taken by $\mathrm{X}$ to complete the whole work be t, then
$2 \times t+1 \times(t-2)+4 \times(t-8)=92$
$2 t+t-2+4 t-32=92$
$7 t=126$
$t=18 \mathrm{hr}$
3 पुरुषों का 1 दिन का काम
$=6$ स्त्रियों का 1 दिन का काम
1 पुरुष का 1 दिन का काम
$=2$ स्त्रियों का 1 दिन का काम
12 पुरुषों व 8 स्त्रियों का 1 दिन का काम
$=32$ स्त्रियों का 1 दिन का काम
$32: 6:: 16: x$
$x=\frac{6 \times 16}{32}=3$ दिन