Free Practice Questions for Time-and-work in Maths

Practice questions here, for every subject and every exam. Unlimited questions for unlimited attempts, given with answers and explanations.


Question 161:

$\mathrm{A}$ and $\mathrm{B}$ can do a piece of work in 12 days and 20 days respectively. They both work together for 6 days. The remaining work is completed by $C$ alone in 12 days. In how many days will $A$ and $C$ together complete the $\frac{2}{3}$ part of the work?

Question 162:

$\mathrm{A}, \mathrm{B}$ and $\mathrm{C}$ individually can complete a work in 12,10 and 15 days, respectively. All three work together and after 3 days, B and $\mathrm{C}$ leave the work. The remaining work will be completed by A in how many days:

Question 163:

5 men 3 women can earn ₹ 8,400 in 4 days. 9 men and 7 women can earn ₹28,700 in 7 days. In how many days will 8 men and 5 women earn ₹ 30,600?

Question 164:

Initially, Rekha works at the rate that she can do a piece of work in $24\mathrm{~h}$, but she does work at that rate only up to $8\mathrm{~h}$. After that, she works at the rate that she can complete the whole work in $9 \mathrm{~h}$. If Rekha has to complete that work in at a stretch, then how many hours will she take  to complete that work?

Question 165:

Seema works at a rate such that she can finish a work in $28 \mathrm{~h}$, but she works at this rate for $7 \mathrm{~h}$ only. After that, she works at a rate such that she can finish the total work in $16 \mathrm{~h}$. If Seema is to finish this work at a stretch, how many hours (total) will she take to finish this work?

Question 166:

$\mathrm{X}$ can complete $\frac{1}{4}$ of a work in 3 days and $Y$ can complete $\frac{1}{6}$ of the same work in 4 days. $X$ and $Y$ worked together for 6 days and $\mathrm{Z}$ alone completed the remaining work in 8 days. If $\mathrm{Y}$ and $\mathrm{Z}$ work together, how much time will they take to complete the same work?

Question 167:

12 persons can dig a trench $20 \mathrm{~m}$ in length in 8 days. The number of persons required to dig a $30 \mathrm{~m}$ trench of the same width and depth in 6 days, is:

Question 168:

Radha who is half as efficient as Kirti, will take 30 days to complete a task if she works alone. If Radha and Kirti work together, how long will they take to complete the task?

Question 169:

10 women can complete a work in 15 days. The same work can be completed in 5 days by 15 men. 10 women started the work and after 3 days, 5 men replaced 5 women. In how many days will the work be completed?

Question 170:

Honey and Junnu together can finish a certain work in 20 days. Honey, having worked for 12 days, Junnu finished the remaining work alone in 36 days. In how many days can Junnu finish the whole work alone?

Question 171:

25 women can do a piece of work in 60 days. After how many days from the start of the work, should 15 more women join them so that the work is done in 45 days?

Question 172:

$\mathrm{A}$ and $\mathrm{B}$ can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete $\frac{4}{9}$ part of the original work in:

Question 173:

An officer undertakes to complete a job in 300 days. He employs 300 people for 60 days and they complete half of the work. He then reduces the number of people to 100 , who work for 120 days, after which there are 20 days' holiday. How many people must be employed for the remaining period to finish the work?

Question 174:

18 persons can complete a work in 15 days when they work 6 hours a day. The time (in days) taken by 12 persons working 10 hours a day to complete the same work, is:

Question 175:

A and B can complete a work in 18 days and 10 days, respectively. They worked together for 5 days, after which B was replaced by C and the work was completed in the next 3 days. How long will C alone take to complete the entire work?

Question 176:

A can do a certain work in 18 days and B can do it in 30 days. They work together for 6 days. The remaining work is completed by C alone in 7 days. In how many days will A, B and C together complete the same work?

Question 177:

A alone can complete a piece of work in 18 days and B alone can complete the same work in 24 days. A and B undertook the work for ₹ 22,500 . They took the help of C and completed the work in 8 days. How much is to be paid to A ?

Question 178:

If 25 men can complete a work in 36 hours, then in how many hours will 12 men complete the same work?

Question 179:

A and B can do a certain work in $22 \frac{1}{2}$ days and 30 days, respectively. They started the work together but after 6 days, B had to leave. Then, A working with $\mathrm{C}$ completed the remaining work in 3 days. $\mathrm{C}$ alone can complete the original work in:

Question 180:

Two men X and Y working together, completed a job in 6 days. If X had worked thrice as efficiently as he actually worked and Y had worked one-fourth as efficiently as he actually worked, the work would have been completed in 4 days. In how many days X alone could complete the work?