Practice questions here, for every subject and every exam. Unlimited questions for unlimited attempts, given with answers and explanations.
Madhur is thrice as good as Manisha, and together they complete a task in 15 days. In how many days will Madhur alone complete the task?
Let efficiency of manisha be $=1$ unit
Madhur is thrice as good as Manisha
So, Efficiency of Madhur $=3$ unit
Total work $=4 \times 15=60$
Madhur alone will complete the task in days $=\frac{60}{3}=20$ days
A and B together can finish a work in 10 days, B and C together can finish the same work in 15 days, and A and C together can finish the same work in 20 days. In how many days can c alone finish the same work?
Let total work be the LCM of 10,15 and $20=60$
Efficiency of $2(\mathrm{~A}+\mathrm{B}+\mathrm{C})=6+4+3=13$
$
(\mathrm{A}+\mathrm{B}+\mathrm{C})=\frac{13}{2}
$
Efficiency of $\mathrm{C}=(\mathrm{A}+\mathrm{B}+\mathrm{C})-(\mathrm{A}+\mathrm{B})$
$
=\frac{13}{2}-6=\frac{1}{2}
$
$\mathrm{C}$ alone finish the work in days $=\frac{60}{\frac{1}{2}}=120$ days
A, B and C working together can complete a work in 16 days. If A and B work together, they can complete the same work in 18 days. If B and C work together they can complete the same work in 24 days. In how many days can A and C complete the same work?
Let the total work be the LCM of 16,18 and 24 = 144.
Efficiency of $\mathrm{A}=(\mathrm{A}+\mathrm{B}+\mathrm{C})-(\mathrm{B}+\mathrm{C})=9-6=3$
Efficiency of $\mathrm{C}=(\mathrm{A}+\mathrm{B}+\mathrm{C})-(\mathrm{A}+\mathrm{B})=9-8=1$
Total efficiency of $\mathrm{A}+\mathrm{C}=3+1=4$
A and C complete the same work $=\frac{144}{4}=36$ days
8 taps having the same flow of water fill a tank in 27 minutes. After 3 minutes, 2 taps went out of service. The time taken to fill the tank by the remaining taps is:
8 taps fill the tank together in 27 minutes.
8 taps fill the tank together in 3 minutes $=\frac{27}{3}=\frac{1}{9}$
Remaining fills in the tank $=1-\frac{1}{9}=\frac{8}{9}$
We know, $\frac{M_1 \times D_1 \times H_1}{W_1}=\frac{M_2 \times D_2 \times H_2}{W_2}$
$
\begin{aligned}
&\Rightarrow \frac{8 \times 27}{1}=\frac{6 \times H}{\frac{8}{9}} \\
&\Rightarrow \mathrm{H}=\frac{8 \times 27 \times 8}{6 \times 9}=32 \text { minutes }
\end{aligned}
$
A's one day's work $=\frac{1}{15}$
B's one day's work $=\frac{1}{20}$
One day's work of both together $=\frac{1}{15}+\frac{1}{20}=\frac{4+3}{60}=\frac{7}{60}$
Kelvin and Kim can together finish a work in 25 days. They worked together for 15 days and then Kim left. After that, Kelvin finished the remaining work in 12 days. In how many days, can Kelvin alone finish the work?
Let the efficiencies of Kelvin and Kim are $x$ and $y$ respectively,
According to question
$25(x+y)=15(x+y)+12 x$
$10(x+y)=12 x$
$10 y=2 x$
$\frac{x}{y}=\frac{10}{2}=\frac{5}{1}$
Total work $=25(5+1)=150$
Time taken by Kelvin to complete the total work, working alone $=\frac{150}{5}=30$ days
Six men can complete a work in 14 days. They started the work and after 5 days, three men left. In how many days will the work be completed by the remaining men?
Let ${x}$ be the required number of days to complete the work.
According to question
$6$ Men $\times 9$ days $=3$ Men $\times x$ days
${x}=18$ days
A can finish a work in 16 days and B can finish the same work in 15 days. After A had worked for 4 days, B also joined A to finish the remaining work. In how many days will the remaining work be finished?
Work done by $A$ in 4 days $=15 \times 4=60$
Remaining work $=240-60=180$
Total efficiency of $\mathrm{A}+\mathrm{B}=15+16=31$
Required days to finished the work by $\mathrm{A}$ and $\mathrm{B}=\frac{180}{31}=5 \frac{25}{31}$ days
A and B together can complete a piece of work in 3 days, while C and D together can complete the same work in 6 days. In how many days can A, B, C and D complete it together?
Let the total work be $6, ($LCM of $3$ and $6)$
Efficiency of $\mathrm{A}$ and $\mathrm{B}=\frac{6}{3}=2$
Efficiency of $\mathrm{C}$ and $\mathrm{D}=\frac{6}{6}=1$
Time taken by $\mathrm{A}, \mathrm{B}, \mathrm{C}$ and $\mathrm{D}$ working together $=\frac{6}{(1+2)}=\frac{6}{3}=2$ days
Let the efficiencies of Men and Women are $M$ and W respectively, then
$
\begin{aligned}
&4(5 W+2 M)=3(6 W+3 M) \\
&20 W+8 M=18 W+9 M \\
&2 W=1 M \\
&\frac{M}{W}=\frac{2}{1}
\end{aligned}
$
Total work $=4(5 W+2 M)=4(5+4)=36$
Time taken by one woman and one man working together to complete the total work $=\frac{36}{(1+2)}=\frac{36}{3}=12$ days
A can complete a work in 8 days. B can complete it in 12 days. With the assistance of C, they completed the work in 4 days. In how many days can C alone complete the same work ?
Total work = LCM of $(8 , 12$ and $4 ) = 24$
Efficiency of $A=\frac{24}{8}=3$
Efficiency of $\mathrm{B}=\frac{24}{12}=2$
Efficiency of $\mathrm{A}+\mathrm{B}+\mathrm{C}=\frac{24}{4}=6$
So, Efficiency of $\mathrm{C}=($ Efficiency of $\mathrm{A}+\mathrm{B}+\mathrm{C})-$ (Efficiency of $(\mathrm{A}+\mathrm{B})=6-5=1$
$C$ complete the work $=\frac{24}{1}=24$ days
Let $x$ men decided to do the work.
By MDH formula ,
$
\begin{aligned}
&\frac{M_1 \times D_1 \times H_1}{W_1}=\frac{M_2 \times D_2 \times H_2}{W_2} \\
&x \times 20=(x-5) \times 24 \\
&4 x=120 \\
&x=30
\end{aligned}
$
So originally there were 30 men.
A and B together can do a certain work in 36 days, whereas B and C together can do it 40 days. A, B and C together can do it in 30 days. B alone can do $\frac{7}{8}$ part of the original work in:
A + B can do a work = 36 days
B+ C can do the same work = 40 days
A+B+C can do it = 30 days
LCM of (36, 40 , 30) = 360
So, Total work = 360
Efficiency of $\mathrm{A}+\mathrm{B}=\frac{360}{36}=10$
Efficiency of $\mathrm{B}+\mathrm{C}=\frac{360}{40}=9$
Efficiency of $\mathrm{A}+\mathrm{B}+\mathrm{C}=\frac{360}{30}=12$
So, efficiency of $\mathrm{C}=($ Efficiency of $\mathrm{A}+\mathrm{B}+\mathrm{C}) - $(Efficiency of $\mathrm{A}+\mathrm{B})$
$
=12-10=2
$
Efficiency of $\mathrm{B}=9-2=7$
B alone can do $\frac{7}{8}$ part of the original work $=\frac{360 \times \frac{7}{8}}{7}$
$=45$ days
75 workers could complete only one-third of a work in 20 days. It is desired that the work be finished in the next 30 days. How many more workers should be taken to complete the work in the desired time ?
By MDH formula,
$
\frac{M_1 \times D_1 \times H_1}{W_1}=\frac{M_2 \times D_2 \times H_2}{W_2}
$
Let the total work be 3 units.
$\frac{75 \times 20}{1}=\frac{30\times[M_2]}{2}$
$
M_2=100
$
So more workers required $=100-75=25$.
$X$ and $Y$ together can do a piece of work in 8 days. If $X$ alone can do the same work in 40 days, then in how many days will $Y$ do the work alone?
Let the total work be 40 unit , then
Efficiency of X $= \frac{40}{40} = 1$
And Efficiency of X+Y $= \frac{40}{8} = 5$
So Efficiency of Y $=5-1=4$
Time taken by Y to complete total work $=\frac{40}{4}=10$ Days
$\mathrm{A}$ and $\mathrm{B}$ can do a piece of work in 12 days and 20 days respectively. They both work together for 6 days. The remaining work is completed by $C$ alone in 12 days. In how many days will $A$ and $C$ together complete the $\frac{2}{3}$ part of the work?
Let the total work $60$ , (LCM of 12 and 20) , then
Efficiency of A $=\frac{60}{12} = 5$
Efficiency of B $=\frac{60}{20} = 3$
A and B worked for 6 days so they completed $6(5+3) = 48$
Remaining work $60-48=12$
Remaining work was completed by C in 12 days so,
Efficiency of C $=\frac{12}{12} = 1$
to complete $\frac{2}{3}$ of the total work ,
The time taken by A and C $=\frac{2}{3}\times\frac{60}{5+1} = \frac{2}{3}\times10 = 6\frac{2}{3}$ days
$X$ and $Y$ together can do a work in $2 \frac{2}{5}$ days, $Y$ and $Z$ together can do the same work in 3 days, and $X$ and $Z$ together can do the same work in 4 days. The time taken by $X, Y$ and $Z$ together to do the same work is:
Efficiency of $X, Y$ and $Z$ $=\frac{5 +4 +3}{2}=\frac{12}{2} = 6$
Therefore, required time taken by $X, Y$ and $Z=\frac{12}{6}=2$ days.
A can complete a piece of work in 7 days and B can complete the same work in 12 days. A and B worked together for 3 days. C alone completed the remaining work in 9 days. How many days will C take to complete the same work entirely?
Work done by $A$ and $B$ in 3 days $=3 \times(12+7)=57$ units
Remaining work $=84-57=27$ units
Efficiency of $C=\frac{27}{9}=3$ units $/$ day
Required time taken by C to complete the whole work $=\frac{84}{3}=28$ days
The ratio of days required by $A$ and $B$ to complete some work is $3: 5$. They need $5 \frac{5}{8}$ days to complete the work. In how many days can $A$ alone do twice the work?
ATQ,
$\begin{array}{cccc} & \mathrm{A} & & \mathrm{B} \\ \text { Days } & 3 & : & 5 \\ \text { Efficency } & 5 & : & 3\end{array}$
$(A+B)$ together complete work $=5 \frac{5}{8}=\frac{45}{8}$ $\times 8$
$
=45 \text { days }
$
A alone do twice the work $=\frac{45}{5} \times 2=18$ days
A and B working together can complete 45% of a work in 18 days. A alone can complete the same work in 60 days. A and B work together for 16 days, and then A leaves. B alone will complete the remaining work in:
Given:
$A$ and $B$ can complete $45 \%$ of a work in $18$ days.
$A$ and $B$ can complete the whole work in $=\frac{18}{45} \times 100=40$ days
A alone can complete the whole work $=60$ days
Let total work $=\mathrm{LCM}$ of $40,60=120$ units
Work done by $A$ in a day $=\frac{120}{60}=2$ units
Work done by $A$ and $B$ in 1 day $=\frac{120}{40}=3$ units
Work done by B in 1 day $=3-2=1$ units
Work done by $A$ and $B$ in 16 days $=16 \times 3=48$ units
Remaining work $=120-48=72$ units
Therefore, required time taken by B to complete remaining work $=\frac{72}{1}=72$ days
Hence, option C is correct.