Practice questions here, for every subject and every exam. Unlimited questions for unlimited attempts, given with answers and explanations.
X is 60% more efficient than Y, and Y alone can do a work in 80 days. Working together, X and Y will complete 52% of the same work in
Let the efficiency of $Y=5$
Efficiency of $X=5 \times \frac{(100+60)}{100}=8$
Total work $=5 \times 80=400 $
Therefore, required time to complete $52 \%$ of the same work by $A$ and $B$ = $\frac{400 \times \frac{52}{100}}{8+5}=400 \times \frac{52}{100} \times \frac{1}{13}=16 \text { days }$
Hence, option A is correct.
14 men complete a work in 18 days. If 21 men are employed, then the time required to complete the same work will be:
Let the time required to complete the same work = x
We know that:
W = MDH
According to question,
Work = work
$\Rightarrow 14 \times 18=21 \times(x)$
$\Rightarrow x=\frac{14 \times 18}{21}$
$\Rightarrow x=12$ days
Therefore, the time required to complete the same work = 12 days
Hence, option D is correct.
Ratio of his wages = 8500 : 6050 = 170 : 121
Ratio of his actual days and working days = 170 : 121
Therefore, he was absent = 170 – 121 = 49 days
Hence, option A is correct.
Work done by $A$ in 1 day $=\frac{1}{60}$
Work done by $A$ in 15 days $=\frac{1}{60} \times 15=\frac{1}{4}$
Remaining work $=1-\frac{1}{4}=\frac{3}{4}$
B can complete $\frac{3}{4}$ th of the work $=30$ days
B can complete whole work $=\frac{30}{3} \times 4=40$ days
Required, time taken by $A$ and $B$ to complete the whole work-
$
\Rightarrow \frac{1}{(A+B)}=\frac{1}{A}+\frac{1}{B}
$
$
\Rightarrow \frac{1}{(A+B)}=\frac{1}{60}+\frac{1}{40}
$
$
\Rightarrow \frac{1}{(A+B)}=\frac{2+3}{120}
$
$
\Rightarrow \frac{1}{(A+B)}=\frac{5}{120}
$
$
\Rightarrow(A+B)=24 \text { Days }
$
Therefore, $A$ and $B$ working together can finish the whole work in 24 days.
Hence, option D is correct.
A and B can complete a task in 12 days, B and C can complete the task in 16 days, A and C can complete the task in 24 days. In how many days will they together complete the task?
According to the question,
Total work = 48
Now, 2(A + B + C) = 9
Efficiency of (A + B + C) = 4.5
So. they will take = $\frac {48}{4.5}$
⇒ 10.67 days
∴ They will take 10.67 days to complete the work.
Kirti and Malti together can complete a work in 12 days, while Malti can complete it in 30 days. In how many days can Kirti alone complete the work?
ATQ,
LCM (12, 30) = 60
(K+M) work together = 5 unit/day
Malti can do work = 2 unit/day
kriti alone complete the work = $\frac{60}{5-2}$
$=\frac{60}{3}=$ 20 day
If 2 men or 3 women can complete a piece of work in 30 days, then in how many days will 6 men and 1 woman be able to complete the same work?
ATQ,
2× 30 Men = 3 × 30 Women
$\frac{\text { Men }}{\text { Women }}$ = $\frac{3}{2}$
Total work = 2 × 3 × 30 = 180 unit
(6 Men + 1 Women) Complete the work
= $\frac{180}{6 \times 3+2 \times 1}$ = $\frac{180}{20}$ = 9 day
A and $B$ can complete a work in 80 days and 96 days, respectively. They completed the work in 32 days with the help of $C$. How many days will C take to complete the entire work alone?
MATHS MIRROR APPROACH -
Let total work $=\operatorname{LCM}(80,96,32)=480$ units
Efficiency of $A=\frac{480}{80}=6$ unit / day
Efficiency of $B=\frac{480}{96}=5$ unit / day
Efficiency of $A+B+C=\frac{480}{32}=15$ unit / day
Efficiency of $C= 15-(6+5) = 4
Number of days taken by C to complete the whole work $=\frac{480}{4}=120$ days
BASIC APPROACH -
Number of days taken by A to complete the whole work $=80$ days
Number of days taken by B to complete the whole work = 96 days
Let total work $=\operatorname{LCM}(80,96)=480$ units
Efficiency of $A=\frac{480}{80}=6$ unit/day
Efficiency of $B=\frac{480}{96}=5$ unit / day
They completed the work in 32 days with the help of C.
Efficiency of $A, B$ and $C$ altogether $=\frac{480}{32}=15$ unit/day
Efficiency of $C=15-6-5=4$ unit/day
Number of days taken by C to complete the whole work $=\frac{480}{4}=120$ days
Train A takes $1 \frac{4}{5}$ th of the time taken by train B to cover a distance of $360 \mathrm{~km}$. If the speed of train A doubles, it will take $36 \mathrm{~min}$ less than the time taken by train B to travel the same distance. What is the speed (in $\mathrm{km} / \mathrm{h}$ ) of train B?
MATHS MIRROR APPROACH:
Time taken by $A = \frac{9}{5}$$\times $$($Time taken by $B)$
Distance =360 km (constant for both)
$\mathrm{A}$ $\mathrm{B}$
$\mathrm{Time}$ $9 \ \ : \ \ 5$
$\mathrm{Speed}$ $5 \ \ : \ \ 9$ (Speed is inversely proportional to time when distance is constant)
When speed of train A doubles -
$\mathrm{A}$ $\mathrm{B}$
$\mathrm{Speed}$ $10 \ \ : \ \ 9$
$\mathrm{Time}$ $9 \ \ : \ \ 10$
ATQ, (10-9) unit = 36 min
1 unit = 36 min
Time taken by train B to cover a distance of $360 \mathrm{~km} $$\Rightarrow 5$ units $= 180$ min $= 3$ hr
Required speed of B = $\frac {360}{3} = 120 \mathrm{~km} / \mathrm{hr}$
BASIC APPROACH:
Train A takes $1 \frac{4}{5}$ hr more than the time taken by train B to cover a distance of $360 \mathrm{~km}$.
Distance $=360 \mathrm{~km}$
Let speed of train $\mathrm{A}=\mathrm{A} \mathrm{km} / \mathrm{hr}$
Speed of train $\mathrm{B}=\mathrm{B} \mathrm{km} / \mathrm{hr}$
As we know,
$\text { Time }=\frac{\text { Distance }}{\text { Speed }}$
$\frac{360}{A}=\frac{360}{B}+\frac{9}{5}$........(1)
If the speed of train A doubles, it will take 36 min less than the time taken by train B to travel the same distance.
$\frac{360}{2 A}=\frac{360}{B}-\frac{36}{60}=\frac{360}{B}-\frac{3}{5}$........(2)
Subtract (2) from (1) -
$\frac{360}{2 A}=\frac{12}{5}$
=$A=180 \times \frac{5}{12}=75 \mathrm{~km} / \mathrm{hr}$
Put the value of $A$ in (1)
=$\frac{360}{75}=\frac{360}{B}+\frac{9}{5}$
=$\frac{360}{B}=\frac{24}{5}-\frac{9}{5}=\frac{15}{5}=3$
=$B=\frac{360}{3}=120 \mathrm{~km} / \mathrm{hr}$
Hence, Speed (in km/h) of train $B=120 \mathrm{~km} / \mathrm{hr}$
$\mathrm{G}$ and $\mathrm{H}$ can do a piece of work in 30 days. If $\mathrm{H}$ alone can do it in 50 days. Then $\mathrm{G}$ alone can do it in days.
If 200 men can build a building in 1024 days, then how many men will be required to build the same building in 256 days?
ATQ,
$M_{1} \times D_{1}=M_{2} \times D_{2}$
$\Rightarrow 200 \times 1024=256 \times M_{2}$
$\Rightarrow M_{2}=\frac{200 \times 1024}{256}$
$M_{2}$ = 800
Two persons Kuldeep and Agarkar working separately can reap a crop in a field in 8 and 12 hours respectively. They work alternately for one hour working hours in which Kuldeep is 9 a.m. If the work starts with, when will the harvesting be over?
ATQ,
$\therefore$ 6.30
14 people can complete a piece of work in 12 days. After working for 4 days, 2 more workers are added to it. In how many days will the work be completed from then?
Number of workers = 14
Number of days = 12
Total work = 14 × 12 = 168
Let the capacity of a worker = 1
So work done in 4 days = 14 × 4 × 1 = 56
Work remaining = 168 - 56 = 112
Number of people coming = 2
Total number of people = 14+2 = 16
Time taken to complete the remaining work = $\frac{112}{16}$ =7 Days
A contractor took a project for 6 months, for which he employed 120 men. Due to the emergency, he was asked to finish the work in 4 months. How many more men should he hire?
ATQ,
$\Rightarrow \mathrm{M}_{1} \times \mathrm{D}_{1}=\mathrm{M}_{2} \times \mathrm{D}_{2}$
$\Rightarrow 120 \times 6=x \times 4$
$\Rightarrow x=\frac{120 \times 6}{4}$
$x=180$
So, more men required =180-120= 60
Five people can build a wall in 24 days. In how many days can eight other people, each of whom is only half as skilled as the people of the first group, be able to build $\frac{3}{5}$ of the wall?
ATQ,
$\Rightarrow \frac{\mathrm{M}_{1} \times \mathrm{D}_{1}}{\mathrm{~W}_{1}}=\frac{\mathrm{M}_{2} \times \mathrm{D}_{2}}{\mathrm{~W}_{2}}$
$\Rightarrow \frac{5 \times 24}{5}=\frac{4 \times \mathrm{D}_{2}}{3}$
$\mathrm{D}_{2}=18$ days
A can do a piece of work in $8 \mathrm{~h}$, while B alone can do the same work in $12 \mathrm{~h}$. If both $A$ and $B$ work together, then in how much time can they finish the work?
ATQ,
$(A+B)$ work together
$\Rightarrow \frac{24}{3+2} \mathrm{hrs}$
$\Rightarrow \frac{24}{5}$ hours $\Rightarrow \frac{24}{5}$
Let total work $=$ LCM of 4,6 and $12=12$ units
Efficiency of $A=\frac{12}{4}=3$ units
Efficiency of $B=\frac{12}{6}=2$ units
Efficiency of $C=\frac{12}{12}=1$ unit
Total time taken by A, B and $C=\frac{12}{3+2+1}=\frac{12}{6}=2$ days
P can complete five-eighths of a work in 15 days and Q can complete three-fourths of the same work in 30 days. They worked together for 8 days and then P left. How much time will Q working alone, take to complete the remaining work?
$P$ can complete five-eighths of a work in 15 days.
Number of days taken by P to complete the whole work $=15 \times \frac{8}{5}=24$ days
Q can complete three-fourths of the same work in 30 days.
Number of days taken by $Q$ to complete the whole work $=30 \times \frac{4}{3}=40$ days
They worked together for 8 days and then P left.
Work completed by $\mathrm{P}$ and $\mathrm{Q}$ together in 8 days $=8 \times(5+3)=64$ units
Remaining work $=120$ units $-64$ units $=56$ units
Number of days taken by $Q$ to complete the remaining work =
$\frac{56}{3}=18 \frac{2}{3}$ days $=18$ days and 16 hours
A certain number of persons can complete a work in 54 days. If there were 15 persons less, it would take 18 days more for the work to be completed. Initially, the number of persons was:
Let total number of person $=x$
Now, according to question,
Total work $=$ total work
$
\Rightarrow(x) \times 54=(x-15) \times(54+18)
$
$\Rightarrow 54 x=(x-15) \times 72$
$
\Rightarrow 3 x=(x-15) \times 4
$
$
\Rightarrow 3 x=4 x-60
$
$
\Rightarrow x=60
$
Therefore, the number of person is 60.
The efficiency of Ram is twice that of Rahim. Ram can complete a work in 6 days. In how many days will Rahim complete the same work?
Given, the efficiency of Ram is twice that of Rahim
Ram alone takes 6 days to complete a piece of work.
1-day work done by individual = Work/time
$\Rightarrow 1$-day work of Ram $=1 / 6$
The efficiency of Ram is twice that of Rahim
$\Rightarrow 1$ day work of Rahim $=1 / 2 \times(1$ day work of $A)=(1 / 2) \times(1 / 6)=1 / 12$
Time taken by Rahim $=12$ days